Budget, costs and change orders (Project management module)

Compare a project's budget with its actual and forecast cost by category and by task, record supplier bills, and create change orders the client signs.

With the Store module Project management, the Budget & costs and Change orders tabs of a project follow the money: what was planned, what was spent, what it will cost at the end, and the changes the client agreed to.

Who can do this: the Budget & costs tab needs See costs & margins. Adding costs, budget lines and change orders needs Manage projects & Gantt. Approving a change order that goes over your approval rules needs Approve change orders.

Budget & costs

  • The tiles show the revised contract (contract plus approved change orders), the actual cost, the forecast cost (with the overrun) and the forecast margin compared with the planned margin.
  • By category: labour, equipment, materials, subcontract and other, with the budget, the actual cost, the % used, the forecast and the variance (red when over budget).
  • Spent vs forecast: one bar per category; the solid part is spent, the light part the forecast, the line the budget.
  • Where actual cost comes from: nothing is typed twice. Labour comes from the time on work billings and time sheets (minutes × each person's cost rate); materials, expenses and rentals from the work-billing items; supplier bills and purchase orders from the list below.
  • By WBS: the budget and costs attached to a task.
  • Budget lines: click Edit to split the cost budget by category (and by task if you want). The lines replace the project's cost budget.
  • Project costs: click Add cost to record a supplier bill, a purchase order or another cost: category, vendor, reference, description, the committed amount (ordered, not billed yet), the actual amount (billed to you), the date and the task. Use the pencil to edit and the bin to delete.
  • Export CSV downloads the categories, the WBS view and the costs.

Change orders

A change order (CO-1, CO-2…) changes the contract after it was signed.

  1. Click New (on the Change orders tab or at the bottom of Budget & costs).
  2. Enter the change, a description, who asked for it (Client, Site or Office), the lines (description, quantity, unit price, unit cost), the schedule impact in days and, if it answers one, the RFI.
  3. Click Save. The change order is a draft.
  4. Open it and click Submit for approval. If the amount or the margin is within your approval rules it is approved at once; otherwise the approver is told and clicks Approve.
  5. Click Send to client. The client gets an email and a notification and signs in the portal or the Vjobo Client app (drawn signature).
  6. When the client signs, the change order is approved: the contract, the cost budget, the end date and the billing schedule are updated. The signature, who signed and when are shown on the change order.

Withdraw stops a change order that isn't approved yet (give the reason). An approved change order can't be withdrawn: make a new one with a negative price instead.